M2 Link: Ballee Road East to M2 Ballymena Bypass Dualling Scheme

Mainline: 2.1 kilometres dual carriageway
Side roads: 0.9 kilometres single carriageway
Total cost: £12.1 million
Contract type: Traditional Consultant design Contractor build
View Partnering Charter (221KB) This link will open a new window. here
Contractor: F P McCann Ltd., Magherafelt
Anticipated completion: Summer 2010
View Construction Photogallery This link will open a new window. here               

Contract status at 28 August 2010: The southbound lane of the new road opened to traffic on Sunday 15 August. The northbound lane of the new road opened to traffic on Tuesday 24 August. Both carriageways will continue to operate under traffic management (single file traffic in each carriageway) over the next two weeks or so. Click here This link will open a new window. to view leaflet on interim traffic arrangements here.