DURING CONSTRUCTION
a
temporary road bridge will be constructed to the south of the junction to carry Grosvenor Road over
Westlink;
two lanes of traffic will be maintained in each direction along
Westlink;
vehicle and pedestrian access will be maintained along Grosvenor
Road but there will be no vehicle connections between these roads
ON COMPLETION
THE JUNCTION WILL HAVE
a dual 3 lane underpass;
a
new bridge carrying Grosvenor Road over Westlink;
a south-bound on slip (for
traffic going towards the M1);
a north-bound off slip (for traffic coming
from the M1).